Construction Update
July 9, 2007

 
 
  Pearl Hall Construction Update
Work is moving forward on all three major campus construction projects. Following are details of recent planning and progress.To see a selection of photos of Pearl Hall site preparation, click the following link: http://www.centre.edu/pearlhall/photos/excavation/excavation.html

--Auxiliary entrance to Hillside is complete.
--Excavation continues on site: approximately 12,000 cubic yards have been excavated.
--Temporary electricity to site has been installed, waiting for KU to connect power.
--Project management meeting was held; engineering meeting scheduled.
--Thermal well drilling scheduled to start July 9.
--Weekly and bi-weekly meeting schedule set for contractors and owner.
--Construction sign showing completed project rendering was installed on site